Not legal advice. No template is compliant out of the box. A SWMS has to be made site-specific with the workers doing the job before work starts. SWMS Kit is not a regulator.

Electrician SWMS Kit · SWMS 01

Work on or near energised electrical installations and services

The SWMS for work on or near live electrical installations — the high risk construction work category that, on its own, means a SWMS is required before the job starts.

Ships as two files: Model WHS (NSW, QLD, SA, TAS, ACT, NT, WA) and a Victorian OHS version. Model category (k). Victorian category 7. Not compliant until you make it specific to the site with the workers doing the work.

First page of SWMS 01 Energised Electrical Work showing the header block and site-specific checklist
SWMS 01 — header block and the make-it-site-specific checklist.

What the task table covers

  • Plan the work and decide whether it must be live. Electric shock, arc flash, unplanned energisation
  • Isolate, lock out and tag out. Someone else re-energises the circuit while you are in it
  • Test for dead. A meter that is faulty, or testing the wrong conductor
  • Work in the restricted zone, if live work is justified. Shock, burns, tools bridging live parts